Project Location: Stourport

Project Scope: 

2,000 square metres of strip off and re-sheet of production facility.

Our Approach

The project consisted of the removal of the property’s existing roof (asbestos cement) to 2,000 square metres, replacing it with a new Kingspan Composite Panel and the installation of new GRP double skin roof lights. The guttering was also replaced.

Removal of existing roof (asbestos cement) to 2,000 square metres and replace with new Kingspan Composite Panel and installation of new GRP double skin roof lights. Removal of guttering and replace with new.

Removal of existing wall cladding and replace with new Kingspan Composite Panel, with all associated architectural feature details.

The removal of existing wall cladding, and replacing it with new Kingspan Composite Panel along with all associated architectural feature designs.

Project Duration: 

12 weeks.