Project Location: Swindon

Project Scope: 

Removal of existing roof (asbestos cement) 10,000 square metres and replace with new Kingspan Composite Panel.

Our Approach

Following client negotiations, commercial discussions and value engineering exercises with the building owners, Profile were awarded this contract.

This Swindon based project involved the removal of the buildings existing wall cladding, and it being replaced with Kingspan Composite Panel along with all associated architectural feature details. 

Whilst the procurement stage was underway, Profile carried out the required safety preparation works, ready in advance of the actual works.

During a 12 week rolling programme the roof was stripped off and replaced. With a Kingspan Solar Panel 250 kwp System fitter on top of the new roof system, the wall cladding and architectural details then followed, which took a further 8 weeks. 

With a robust Profile project team effectively managing the process from start to finish, the project was handed back to the client on time and within the original cost plan agreement.

Project Duration: 

20 weeks.